Xagio SEO - AI Powered SEO 7.1.0.21

Does Xagio SEO - AI Powered SEO work with WordPress 6.8.2 and PHP 8.1.12? A smoke test was performed on .

Summary

Errors
1PHP fatal errors
22PHP warnings
3PHP notices
9PHP deprecation warnings
2Database errors
No JavaScript exceptions
All test pages loaded successfully
No resource errors
Performance

Memory usage: 1.08 MiB
The average PHP memory usage increased by this amount after activating by the plugin.

Page speed impact: 0.161 seconds
The average page load time increased by this amount after activating the plugin.

Environment
WordPress version6.8.2
PHP version8.1.12
MySQL version10.6.10
PHP memory limit512M
Plugin Info
Last updated
Active installs 8,000+
WordPress.org page https://wordpress.org/plugins/xagio-seo/
Badges

WordPress compatibility badge PHP compatibility badge

Get badge code

Pages 18

Plugins ‹ Test site — WordPress

Page screenshot: Plugins ‹ Test site — WordPress
URL /wp-admin/plugins.php?plugin_status=all&paged=1&s
Requested URL /wp-admin/plugins.php?action=activate&plugin=xagio-seo%2Fxagio-seo.php&plugin_status=all&paged=1&s&_wpnonce=edf0e144c6
Aspect after-activation
HTTP status 200
Load time 0.952 s
Memory usage 12.57 MiB
JS errors None
Resource errors None

Xagio

Page screenshot: Xagio
URL /wp-admin/admin.php?page=xagio-dashboard
Aspect menu-item
HTTP status 200
Load time 1.219 s
Memory usage 4.69 MiB
JS errors None
Resource errors None

Xagio → Agent X

Page screenshot: Xagio → Agent X
URL /wp-admin/admin.php?page=xagio-ocw
Aspect menu-item
HTTP status 200
Load time 0.607 s
Memory usage 4.69 MiB
JS errors None
Resource errors None

Xagio → Xagio Settings

Page screenshot: Xagio → Xagio Settings
URL /wp-admin/admin.php?page=xagio-settings
Aspect menu-item
HTTP status 200
Load time 0.398 s
Memory usage 4.74 MiB
JS errors None
Resource errors None

Xagio → SEO Settings

Page screenshot: Xagio → SEO Settings
URL /wp-admin/admin.php?page=xagio-seo
Aspect menu-item
HTTP status 200
Load time 0.685 s
Memory usage 4.69 MiB
JS errors None
Resource errors None

Xagio → Project Planner

Page screenshot: Xagio → Project Planner
URL /wp-admin/admin.php?page=xagio-projectplanner
Aspect menu-item
HTTP status 200
Load time 1.622 s
Memory usage 5.12 MiB
JS errors None
Resource errors None

Xagio → Niche Hunter

Page screenshot: Xagio → Niche Hunter
URL /wp-admin/admin.php?page=xagio-nichehunter
Aspect menu-item
HTTP status 200
Load time 0.592 s
Memory usage 4.69 MiB
JS errors None
Resource errors None

Xagio → Sitemaps

Page screenshot: Xagio → Sitemaps
URL /wp-admin/admin.php?page=xagio-sitemaps
Aspect menu-item
HTTP status 200
Load time 0.276 s
Memory usage 4.69 MiB
JS errors None
Resource errors None

Xagio → 301 & 404

Page screenshot: Xagio → 301 & 404
URL /wp-admin/admin.php?page=xagio-redirects
Aspect menu-item
HTTP status 200
Load time 0.223 s
Memory usage N/A
JS errors None
Resource errors None

Xagio → Silo Builder

Page screenshot: Xagio → Silo Builder
URL /wp-admin/admin.php?page=xagio-silobuilder
Aspect menu-item
HTTP status 200
Load time 0.520 s
Memory usage 4.69 MiB
JS errors None
Resource errors None

Xagio → Link Manager

Page screenshot: Xagio → Link Manager
URL /wp-admin/admin.php?page=xagio-linkmanagement
Aspect menu-item
HTTP status 200
Load time 0.279 s
Memory usage 4.69 MiB
JS errors None
Resource errors None

Xagio → Reviews

Page screenshot: Xagio → Reviews
URL /wp-admin/admin.php?page=xagio-reviews
Aspect menu-item
HTTP status 200
Load time 0.558 s
Memory usage 4.69 MiB
JS errors None
Resource errors None

Xagio → Backup & Restore

Page screenshot: Xagio → Backup & Restore
URL /wp-admin/admin.php?page=xagio-backups
Aspect menu-item
HTTP status 200
Load time 0.309 s
Memory usage 4.69 MiB
JS errors None
Resource errors None

Xagio → Clone

Page screenshot: Xagio → Clone
URL /wp-admin/admin.php?page=xagio-clone
Aspect menu-item
HTTP status 200
Load time 0.277 s
Memory usage 4.69 MiB
JS errors None
Resource errors None

Xagio → Rescue Center

Page screenshot: Xagio → Rescue Center
URL /wp-admin/admin.php?page=xagio-rescuecenter
Aspect menu-item
HTTP status 200
Load time 1.619 s
Memory usage 10.32 MiB
JS errors None
Resource errors None

Test site – Just another WordPress site

Page screenshot: Test site – Just another WordPress site
URL /
Aspect front-page
HTTP status 200
Load time 0.403 s
Memory usage 4.11 MiB
JS errors None
Resource errors None

Add Post ‹ Test site — WordPress

Page screenshot: Add Post ‹ Test site — WordPress
URL /wp-admin/post-new.php
Aspect new-meta-boxes
HTTP status 200
Load time 0.906 s
Memory usage 6.95 MiB
JS errors None
Resource errors None

Add Page ‹ Test site — WordPress

Page screenshot: Add Page ‹ Test site — WordPress
URL /wp-admin/post-new.php?post_type=page
Aspect new-meta-boxes
HTTP status 200
Load time 0.873 s
Memory usage 6.94 MiB
JS errors None
Resource errors None

Benchmark

URL Load time Memory usage
Inactive Active Change Inactive Active Change
/wp-admin/index.php0.343 s0.808 s+0.465 s3.51 MiB4.69 MiB+ 1.19 MiB
/wp-admin/edit.php0.199 s0.299 s+0.100 s3.57 MiB4.69 MiB+ 1.12 MiB
/wp-admin/post-new.php0.776 s1.546 s+0.770 s6.06 MiB6.95 MiB+ 914.96 KiB
/wp-admin/upload.php0.581 s0.456 s-0.125 s3.52 MiB4.69 MiB+ 1.17 MiB
/wp-admin/options-writing.php0.229 s0.544 s+0.315 s3.5 MiB4.69 MiB+ 1.19 MiB
/wp-admin/media-new.php0.278 s0.284 s+0.006 s3.49 MiB4.69 MiB+ 1.2 MiB
/wp-admin/edit-tags.php?taxonomy=category0.249 s0.261 s+0.012 s3.5 MiB4.7 MiB+ 1.19 MiB
/wp-admin/post-new.php?post_type=page0.609 s0.884 s+0.275 s6.05 MiB6.94 MiB+ 910.48 KiB
/wp-admin/options-discussion.php0.374 s0.349 s-0.025 s3.5 MiB4.69 MiB+ 1.19 MiB
/wp-admin/edit-comments.php0.513 s0.278 s-0.235 s3.52 MiB4.69 MiB+ 1.17 MiB
/0.366 s0.577 s+0.211 s3.43 MiB4.11 MiB+ 695.46 KiB
Average 0.411 s0.571 s+0.161 s3.97 MiB5.05 MiB+ 1.08 MiB

Code Statistics

Note: Third-party libraries and minified JS/CSS files are excluded from these statistics where possible, so the numbers you see here may be lower than those reported by other tools.

PHP
JavaScript
CSS
Language % Lines of code Comment lines Files
PHP48.1%42,2996,01064
JavaScript29.3%25,82175928
CSS20.4%17,98035922
JSON1.9%1,68201
XSLT0.1%12321
SVG0.1%90088
XML0.0%1242
HTML0.0%1101
Total 88,018 7,134 207

PHP Code Analysis | More results »

Lines of code 27,947
Total complexity 5,122
Median class complexity 51.0
Median method complexity 4.0
Most complex class XAGIO_API
Most complex function XAGIO_MODEL_OCW::runWizard()
Classes 43
Methods 823
Functions 50

Additions

Things that the plugin adds to the site. This section is not intended to be comprehensive. The test tool only looks for a few specific types of added content.

Database Tables 13

Options wp_options 13

Meta Boxes

{
    "post": {
        "xagio_seo": {
            "title": "Xagio",
            "context": "advanced"
        }
    },
    "page": {
        "xagio_seo": {
            "title": "Xagio",
            "context": "advanced"
        }
    }
}

PHP Error Log 46 lines

[14-Aug-2025 12:05:36 UTC] WordPress database error Unknown column 'reference' in 'where clause' for query SELECT * FROM xag_log_404s WHERE reference != '' made by activate_plugin, do_action('activate_xagio-seo/xagio-seo.php'), WP_Hook->do_action, WP_Hook->apply_filters, XAGIO_CORE::activate, XAGIO_CORE::loadModels, XAGIO_MODEL_LOG404::createTable
[14-Aug-2025 12:05:41 UTC] PHP Warning:  foreach() argument must be of type array|object, bool given in /wp-content/plugins/xagio-seo/modules/ocw/page.php on line 1721
[14-Aug-2025 12:05:47 UTC] PHP Notice:  Function wpdb::prepare was called <strong>incorrectly</strong>. The query argument of wpdb::prepare() must have a placeholder. Please see <a href="https://developer.wordpress.org/advanced-administration/debug/debug-wordpress/">Debugging in WordPress</a> for more information. (This message was added in version 3.9.0.) in /wp-includes/functions.php on line 6121
[14-Aug-2025 12:05:47 UTC] PHP Notice:  Function wpdb::prepare was called <strong>incorrectly</strong>. The query argument of wpdb::prepare() must have a placeholder. Please see <a href="https://developer.wordpress.org/advanced-administration/debug/debug-wordpress/">Debugging in WordPress</a> for more information. (This message was added in version 3.9.0.) in /wp-includes/functions.php on line 6121
[14-Aug-2025 12:05:48 UTC] PHP Warning:  Undefined variable $country in /wp-content/plugins/xagio-seo/modules/nichehunter/page.php on line 1017
[14-Aug-2025 12:05:48 UTC] PHP Deprecated:  preg_replace(): Passing null to parameter #3 ($subject) of type array|string is deprecated in /wp-includes/kses.php on line 1807
[14-Aug-2025 12:05:50 UTC] PHP Fatal error:  Uncaught TypeError: implode(): Argument #2 ($array) must be of type ?array, bool given in /wp-content/plugins/xagio-seo/modules/redirects/page.php:221
Stack trace:
#0 /wp-content/plugins/xagio-seo/modules/redirects/page.php(221): implode()
#1 /wp-content/plugins/xagio-seo/helpers.php(566): require_once('...')
#2 /wp-includes/class-wp-hook.php(324): xagio_load_page()
#3 /wp-includes/class-wp-hook.php(348): WP_Hook->apply_filters()
#4 /wp-includes/plugin.php(517): WP_Hook->do_action()
#5 /wp-admin/admin.php(260): do_action()
#6 {main}
  thrown in /wp-content/plugins/xagio-seo/modules/redirects/page.php on line 221
[14-Aug-2025 12:05:54 UTC] PHP Notice:  Function wpdb::prepare was called <strong>incorrectly</strong>. The query argument of wpdb::prepare() must have a placeholder. Please see <a href="https://developer.wordpress.org/advanced-administration/debug/debug-wordpress/">Debugging in WordPress</a> for more information. (This message was added in version 3.9.0.) in /wp-includes/functions.php on line 6121
[14-Aug-2025 12:05:55 UTC] WordPress database error You have an error in your SQL syntax; check the manual that corresponds to your MariaDB server version for the right syntax to use near ''xag_reviews'' at line 1 for query SELECT COUNT('id') FROM 'xag_reviews' made by do_action('admin_post_xagio_getReviews'), WP_Hook->do_action, WP_Hook->apply_filters, XAGIO_MODEL_REVIEWS::getReviews_Datatables
[14-Aug-2025 12:06:03 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 173
[14-Aug-2025 12:06:03 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 174
[14-Aug-2025 12:06:03 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 196
[14-Aug-2025 12:06:03 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 217
[14-Aug-2025 12:06:03 UTC] PHP Deprecated:  Automatic conversion of false to array is deprecated in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1556
[14-Aug-2025 12:06:03 UTC] PHP Deprecated:  Automatic conversion of false to array is deprecated in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1583
[14-Aug-2025 12:06:03 UTC] PHP Warning:  foreach() argument must be of type array|object, bool given in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1586
[14-Aug-2025 12:06:10 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 173
[14-Aug-2025 12:06:10 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 174
[14-Aug-2025 12:06:10 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 196
[14-Aug-2025 12:06:10 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 217
[14-Aug-2025 12:06:10 UTC] PHP Deprecated:  Automatic conversion of false to array is deprecated in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1556
[14-Aug-2025 12:06:10 UTC] PHP Deprecated:  Automatic conversion of false to array is deprecated in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1583
[14-Aug-2025 12:06:10 UTC] PHP Warning:  foreach() argument must be of type array|object, bool given in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1586
[14-Aug-2025 12:06:15 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 173
[14-Aug-2025 12:06:15 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 174
[14-Aug-2025 12:06:15 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 196
[14-Aug-2025 12:06:15 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 217
[14-Aug-2025 12:06:15 UTC] PHP Deprecated:  Automatic conversion of false to array is deprecated in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1556
[14-Aug-2025 12:06:15 UTC] PHP Deprecated:  Automatic conversion of false to array is deprecated in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1583
[14-Aug-2025 12:06:15 UTC] PHP Warning:  foreach() argument must be of type array|object, bool given in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1586
[14-Aug-2025 12:06:20 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 173
[14-Aug-2025 12:06:20 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 174
[14-Aug-2025 12:06:20 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 196
[14-Aug-2025 12:06:20 UTC] PHP Warning:  Trying to access array offset on value of type bool in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 217
[14-Aug-2025 12:06:20 UTC] PHP Deprecated:  Automatic conversion of false to array is deprecated in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1556
[14-Aug-2025 12:06:20 UTC] PHP Deprecated:  Automatic conversion of false to array is deprecated in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1583
[14-Aug-2025 12:06:20 UTC] PHP Warning:  foreach() argument must be of type array|object, bool given in /wp-content/plugins/xagio-seo/modules/seo/metabox/seo.php on line 1586
See also: All tests for this plugin